1. A proposal shall be valid for a period of 90 days from the date set for proposal opening. If a proposal is withdrawn within said period, the initial financial guarantee shall not be returned. Government Tenders and Procurement Law 2. A government agency may extend the proposals’ validity period for another 90 days. Bidders willing to proceed with the tender shall extend the validity period of their initial guarantees.