Government Tenders and Procurement Law
Art. 59Status unknownSaudi ArabiaRegulation
Issued by Ministry of Investment (misa.gov.sa)
1. A contract shall be concluded between a government agency and the
winning bidder after the bidder is notified of the awarding decision and
submits the final letter of guarantee.
2. In public construction contracts, a contractor shall be allowed to commence
execution of the contract within 60 days from the date of being notified of the
awarding decision, unless otherwise stipulated in the tender documents.
The Arabic text is the legally binding version. The English translation is provided for guidance only.