Contracts may be extended and fines may be waived in the following cases:
1. If the contractor is assigned additional work. In such case, the extension
period shall take into consideration the volume and nature of such work and
the date of assignment.
2. If the project’s annual appropriations are insufficient to complete the work
within the specified time.
3. If the delay is attributable to the government agency or to exigent
circumstances.
4. If the delay is attributable to reasons beyond the contractor’s control.
5. If the government agency orders suspension of the work, or part thereof, for
reasons not attributable to the contractor.
The Regulations shall set the controls and procedures for contract extension
and fine waiver.
Government Tenders and Procurement Law
Chapter 7: Partial Withdrawal and Execution at the Contractor’s Expense
The Arabic text is the legally binding version. The English translation is provided for guidance only.
Freshness not yet recorded