Alqanoni

Law of Selling and Leasing Off Plan Real Estate Projects

Art. 13
Status unknownSaudi ArabiaRegulation

Issued by Ministry of Investment (misa.gov.sa)

A developer may, upon the competent authority’s approval, withdraw any amounts in excess of the total actual cost required to complete the real estate project and its amenities, pursuant to a report from the contractor and the consulting firm, provided that the certified public accountant retains in the escrow account an amount equal to 20 percent until the completion of the project.

The Arabic text is the legally binding version. The English translation is provided for guidance only.

Freshness not yet recorded

Related articles

Citing judgments

No judgments citing this article have been indexed yet.

Amendment timeline

No amendment history recorded.