A developer may, upon the competent authority’s approval, withdraw any amounts in excess
of the total actual cost required to complete the real estate project and its amenities, pursuant
to a report from the contractor and the consulting firm, provided that the certified public
accountant retains in the escrow account an amount equal to 20 percent until the completion
of the project.