Saudi Arabian Grid Code May 2024
Para. 3.3.4Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
Consolidation and Maintenance of Grid Planning Data
3.3.4.1 The TSP shall collate and process the Grid Planning Data submitted by the
Users into a cohesive and consolidated Grid planning dataset and shall use
this for conducting the various planning studies and also for preparing any
forecast statements and capacity development/reinforcement plans for the
Transmission System.
3.3.4.2 If any User believes that the cohesive Forecast Data prepared by the TSP
does not accurately reflect that User’s planning data, it shall immediately
notify the TSP of its concern. The TSP and the User shall promptly meet to
address the concern of the User.
3.3.5 Planning Criteria and Standards
The TSP shall apply the TSP Planning Criteria and Standards (established by
the TSP and approved by SERA), in the planning and development of the
Transmission System.