Saudi Arabian Grid Code May 2024
Para. 3.3.3Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
Submission of Grid Planning Data
3.3.3.1 For the TSP to undertake planning and development of the Grid, the TSP will
require the Users to provide data and information before Connection, and
also afterwards at regular intervals. These data will be provided to the TSP
using the schedules provided for this purpose in Chapter 6: Data and
Information Code. These data and information will be treated as Grid
Planning Data.
Chapter 3 - Planning Code
The Saudi Arabian Grid Code
Updated Version: May 2024
3.3.3.2 For planning purposes, Grid Planning Data will be classified into three (3)
main categories: (i) Project Planning Data; (ii) Standard Planning Data; and
(iii) Detailed Planning Data. These data categories are further explained
below:
(i)
Project Planning Data: The TSP will require Users applying for a new,
or modification of an existing, Connection, to submit some or all of the
data items listed under Standard Planning Data and Detailed Planning
Data in this chapter. Such data will be treated by the TSP as Project
Planning Data until a User is actually connected to the Grid.
(ii)
Standard Planning Data: Standard Planning Data are data that must
be submitted by all existing Users at regular intervals.
(iii)
Detailed Planning Data: Detailed Planning Data are data that the TSP
may require from any existing User in support of the Standard
Planning Data.
3.3.3.3 As regards the Project Planning Data, the TSP may require different levels of
detail and quality of information through the various stages of the User
Development, as elaborated on below:
(i)
At the time a User applies for a new, or modification of an existing,
Connection but before the TSP makes an Offer of Connection, the
data relating to the proposed User Development will be considered
Preliminary Project Planning Data and shall contain such data as may
be required by the TSP to evaluate the Connection application and, if
applicable, any other data directly relevant to, and submitted in
support of, the application. These data will be treated by the TSP as
confidential within the scope of TSP’s policy for confidentiality.
(ii)
On formal acceptance by the prospective User of the Offer of
Connection, the data relating to the User Development, previously
submitted as Preliminary Planning Data, including any subsequent
data supplied in support of its application, will become Committed
Project Planning Data. Data at this stage will not be treated as
confidential to the extent that the TSP is required to use or disclose
these to discharge its contractual or regulatory obligations.
(iii)
As soon as is practical, and not later than the Operational Date, all
data requirements as stated in this section, not previously requested
by the TSP or supplied by the User, will be submitted by the User to
The Arabic text is the legally binding version. The English translation is provided for guidance only.