Saudi Arabian Grid Code May 2024
Para. 2.7.8Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
Site Operational Procedures
The TSP and the Users must make available staff to take necessary Safety
Precautions and carry out operational duties as may be required to enable
work/Testing to be carried out and for the operation of Plant and/or Apparatus
connected to the System.
Chapter 2 - Connection Code
The Saudi Arabian Grid Code
Updated Version: May 2024
User submits to TSP
completed application form
along with applicable fees.
Figure 2.6. Procedure for Connection to the Grid
Energization
Connection Agreement between
User and TSP is signed.
Preparation of project
documents by User.
Completion of User
Development work.
User submits Readiness to
Connect statement with
Commissioning Tests Reports.
TSP issues Technical
Completion Certificate.
TSP evaluates User
application.
TSP conducts Grid
Impact Studies.
Application returned
with suggestions for
revision, if
practicable.
TSP and User meet
to resolve dispute.
User revises the
application.
Yes
No
Additional study
Application
acceptable?
User
accepts?
Dispute
resolved
Yes
Yes
No
No
Yes
TSP makes Offer of
Connection to User.
No
No
User
accepts to
pay?
Additional
Study
Required?
Yes
TSP and User
meet
Dispute
resolved?
Yes
No
Yes
User application
rejected
Case closed
Yes
No
User may
approach GCSC
No
Offer
accepted?
User
accepts?
Chapter 2 - Connection Code
The Saudi Arabian Grid Code
Updated Version: May 2024
APPENDIX A2.1: Preparation of Site Responsibility Schedules
A2.1.1
Principles
A2.1.1.1
At all Sites, the following Site Responsibility Schedule shall be drawn up
using the Pro forma Table A2.1 or with such variations as may be agreed
between the TSP and Users. In the absence of agreement, the Pro forma
Table A2.1 shall be used:
(i)
Schedule of (E)HV Apparatus;
(ii)
Schedule of LV Plant, Apparatus, services and supplies;
(iii)
Schedule of telecommunications and measurement Apparatus.
A2.1.1.2
Each Site Responsibility Schedule for a Connection Site shall be prepared
by the TSP in consultation with other Users at least one (1) month prior to
the Completion Date under the Connection Agreement for that Connection
Site (which may form part of a Site).
A2.1.1.3
Each User shall, in accordance with the timing requirements of the
Connection Agreement, provide information to the TSP to enable it to
prepare the Site Responsibility Schedule.
A2.1.1.4
Each Site Responsibility Schedule shall be subdivided to take account of
any separate Connection Sites on that Site.
A2.1.1.5
Each Site Responsibility Schedule shall detail for each item of Plant
and/or Apparatus:
(i)
Plant/Apparatus ownership;
(ii)
Responsible Manager (Controller);
(iii)
Safety standards (applicable Safety Rules and standards);
(iv)
Responsible person(s) responsible for coordinating on Safety
matters;
(v)
operations (applicable operational procedures and Control
Engineer); and
(vi)
responsibility to undertake maintenance.
A2.1.1.6
The (E)HV Apparatus Site Responsibility Schedule for each Connection
Site must include lines and cables emanating from the Connection Site.
A2.1.1.7
Every page of the Site Responsibility Schedule shall bear the date of
issue and the issue number.
A2.1.1.8
When a Site Responsibility Schedule is prepared, it shall be sent by the
TSP to the Users involved for confirmation of its accuracy.
The Arabic text is the legally binding version. The English translation is provided for guidance only.