Saudi Arabian Grid Code May 2024
Para. 6.5.4Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
If a User fails to supply data when that User is required to provide that to the
TSP, the TSP will estimate such data if and when, in the view of the TSP, it is
necessary to do so.
6.5.5 If the TSP fails to supply data to a User, the User to whom that data ought to
have been supplied, will estimate such data if and when, in the view of that
User, it is necessary to do so.
6.5.6 Such estimates will, in each case be based upon data supplied previously for
the same Plant or Apparatus or using corresponding data for similar Plant
and/or Apparatus or such other information as the TSP or User, as the case
may be, deems appropriate.
6.5.7 The TSP will advise a User in writing of any estimated data it intends to use
relating directly to that User Plant and/or Apparatus in the event of data not
supplied.
6.5.8 The User will advise the TSP in writing of any estimated data it intends to use
in the event of data not supplied.
6.5.9 Any risk associated with the use of estimated data will be borne by the party
that has failed to provide the required data.
Chapter 6 - Data and Information Exchange Code
The Saudi Arabian Grid Code
Updated Version: May 2024
6.5.10 Wherever practicable, Users, while submitting data, should identify the
recognized national or international standard to which their Plant, Equipment,
and/or Apparatus was designed.
Data and Information to be Registered
6.6.1 The following Schedules shall be supplied by Users (Generation, Distribution
Entities, and Directly-connected Customers) to the TSP and will cover the
required data for each User:
(i)
Schedule 1: Generating Unit Technical Data. This shall comprise
Generating Unit/Station fixed parameters.
(ii)
Schedule 2: Generating Unit/Station Outage Data. This shall
comprise Generating Unit/Station Equipment Outage Planning Data.
(iii)
Schedule 3: Generation Operation Schedule Data. This shall
comprise data required for the preparation of the Generation
Schedule.
(iv)
Schedule 4: Generation Operational Planning Data. This shall
comprise Generating Unit/Station parameters required for Operational
Planning.
(v)
Schedule 5: User System Data. This shall comprise electrical
parameters relating to Plant and Apparatus connected to the
Transmission System.
(vi)
Schedule 6: Connection Point Data. This shall comprise data
related to Demand and Demand transfer capability.
(vii)
Schedule 7: Demand Control Data. This shall comprise data
relating to Demand Control.
(viii)
Schedule 8: Scheduling and Dispatch Data. This shall comprise
parameters required for Scheduling and Dispatch of Generating
Unit/Station.
(ix)
Schedule 9: Load Characteristics Data. This shall comprise
estimated parameters of loads in respect of Harmonic content,
sensitivity, etc.
Chapter 6 - Data and Information Exchange Code
The Saudi Arabian Grid Code
Updated Version: May 2024
(x)
Schedule 10: Fault Infeed Data. This shall comprise data related to
short circuit infeed of User Equipment to the Transmission System.
(xi)
Schedule 11: User Demand Profiles and Active Energy Data. This
shall comprise data related to Demand profiles.
6.6.2 The following Schedule shall be made available by the TSP to Users:
(i)
Schedule 12: Data Supplied by the TSP to all Users. This shall
comprise data supplied by the TSP to Users.
The Arabic text is the legally binding version. The English translation is provided for guidance only.