Saudi Arabian Grid Code May 2024
Para. 5.2Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
Overview of the Dispatch Process
Instructions
accepted
by
Generator?
TSP issues Dispatch
Instructions to
Generator
Dispatch
Instructions to
Synchronize/
Desynchronize
Generator
Synchronizes
Active/Reactive
Power Dispatch
Operating Mode
Dispatch
Parameter changes
Instructions for
Demand Reduction,
Disconnection, and
Restoration
The entity discusses with
TSP, and TSP issues
new Instructions
TSP revises
Instructions,
if possible
Generator
discusses and
clarifies to TSP
TSP issues Dispatch
Instructions to
Distribution Entities/
Directly-connected
Customers.
System Emergency
Conditions
Additional
Instructions
The entity takes
action
Instructions for Load
Transfer between
Connection Points
Instructions for
Switching in Load
Shedding Scheme
The entity
achieves target
Any
unforeseen
problems?
Informs the TSP
Generator
achieves
target
Generator
complies with
Instructions
Yes
Yes
Yes
NO
NO
NO
Can
Generator
Synchronize
within10
minutes?
Chapter 5 - Scheduling and Dispatch Code
The Saudi Arabian Grid Code
Updated Version: May 2024
APPENDIX A5.1: Generating Block/Unit Declaration
A5.1.1 Availability Notice
(i)
Generating Availability, (start time and date).
(ii)
Generating Unit regime unavailability, (day, start time, end time).
(iii)
Generating Unit initial conditions (time required for Notice to
Synchronize and from Start-up to Synchronize).
(iv)
Maximum Generation increase in output above declared Availability.
(v)
Any changes to Primary Response and Secondary Response
characteristics.
A5.1.2 Scheduling and Dispatch Parameters
(i)
Generating Unit inflexibility (inflexibility description, start date and
time, end date and time, MW);
(ii)
Generating Unit Synchronizing intervals (hot time interval, off-load
time interval);
(iii)
Station Generating Unit De-Synchronizing intervals;
(iv)
Generating Unit basic data:
(a)
Minimum Generation;
(b)
Minimum Shutdown time;
(v)
Generating Unit duty-cycle limitation;
(vi)
Generating Unit minimum on time;
(vii)
Generating Unit Synchronizing MW;
(viii)
Generating Unit Synchronizing groups;
(ix)
Generating Unit run-up rates with MW breakpoints;
(x)
Generating Unit run-down rates with MW breakpoints;
(xi)
Generating Unit loading rates covering the range from Minimum
Generation to Net Dependable Power Capacity;
(xii)
Generating Unit de-loading rates covering the range from Net
Dependable Power Capacity to Minimum Generation.
Chapter 6 - Data and Information Exchange Code
The Saudi Arabian Grid Code
Updated Version: May 2024
CHAPTER 6
DATA AND INFORMATION EXCHANGE CODE
Introduction
6.1.1 The proper and timely exchange of data and information between the TSP
and Users is critical for ensuring non-discriminatory access to the
Transmission System and the safe and reliable provision of Transmission
services. This chapter, therefore, sets out the obligations and responsibilities
of the TSP and Users in relation to the supply of data and information to each
other, and also lists the various categories of data and information to be
exchanged between the TSP and the Users.
6.1.2 The data which is specified in different chapters of the Grid Code are collated
here in this chapter. The relevant chapters also specify the procedures and
timings for the supply of the requisite data.
6.1.3 The various chapters of the Grid Code also specify the information that the
TSP will supply to Users. This information is summarized in a single schedule
in this chapter.
6.1.4 The data listed in the various chapters of the Grid Code contain only the
typical range of data which may be required by the TSP. The actual data
required will be advised by the TSP at the time of assessment of the User
application for new, or modification of an existing, Connection.