Saudi Arabian Grid Code May 2024
Para. 5.4.6Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
Additional Dispatch Instructions
In addition to Dispatch Instructions relating to Dispatch of Active Power and
Reactive Power, Dispatch Instruction may also include those relating to the
following:
(i)
Reserve: Details of the reserve to be carried by each Generating Unit/
Station including specification of the timescale in which that reserve
may be transferable into increased Generating Unit/Station output.
(ii)
System Services: An instruction for a User to provide System
Services.
(iii)
Secondary Control Mode: A requirement for change to or from
Secondary Control Mode for each Generating Unit.
(iv)
Tests: An instruction to carry out tests as required under section (4.8)
or (4.9) of Chapter 4: Operating Code.
System Emergency Conditions
In order to maintain Transmission System integrity under System
Emergency Conditions, the TSP may issue Dispatch Instructions to
Generators to operate outside the limits implied by the then current
Declarations. When issuing such a Dispatch Instruction, the TSP shall
inform the Generator that the Dispatch Instructions is being issued under
System Emergency Conditions.
Where the TSP has issued a Dispatch Instructions in accordance with the
provisions for System Emergency Conditions requiring operation of a
Generating Unit outside the limits applied by the then applicable
Chapter 5 - Scheduling and Dispatch Code
The Saudi Arabian Grid Code
Updated Version: May 2024
Declarations, then the Generator must comply with the Dispatch
Instructions.
Generating Unit/Station Parameter Changes
Each Generator at its Generating Unit/Station will without delay notify the
TSP by telephone of any change or loss (temporary or otherwise) to the
operational capability including any changes to the Scheduling and
Dispatch Parameters of each Generating Unit which is Synchronized or has
been instructed to Synchronize within the next three (3) hours.
If, for any reason, including a change of Availability or Scheduling and
Dispatch Parameters made by the Generator, the prevailing Dispatch
Instruction in respect of any Generating Unit is no longer within the
applicable Availability or Scheduling and Dispatch Parameters then:
(i)
the Generator will use reasonable endeavors to secure that a revised
Dispatch Instruction is issued by the TSP such that the new Dispatch
Instruction is within the now applicable Availability and/or Scheduling
and Dispatch Parameters; and
(ii)
if the TSP fails to issue such a new Dispatch Instruction within a
reasonable time then the relevant Generator shall be entitled to
change the operation of such Generating Unit to bring its operation
within the applicable Availability and/or Scheduling and Dispatch
Parameters until the TSP issues a new Dispatch Instruction within the
applicable Availability and/or Scheduling and Dispatch Parameters.
Prior to making such a change in operation, the Generator will use
reasonable endeavors to advise the TSP (by telephone and then
confirming it by fax) of its intended action and the timing of the
intended action.
The Arabic text is the legally binding version. The English translation is provided for guidance only.