Alqanoni

District Cooling Services Supply Code

Clause 4
Status unknownSaudi ArabiaRegulation

Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)

APPLICATION FOR SUPPLY CONNECTION 4-1 Any person within the service area applying for supply connection to the System is required to submit a formal application through a Professional Engineer to the Licensee. The application shall contain the following information: (a) Location and type of the development; (b) Target supply date; (c) Projected demand growth; (d) Typical daily load pattern; and (e) Typical annual usage pattern 4-2 Upon receipt of an application for supply connection, the Licensee: (a) May require additional information to be submitted by the Applicant; (b) Shall advise the Applicant of the connection scheme, technical requirements and the indicative connection charges. (c) shall use its best endeavour to respond to an application for supply connection within 14 days. 4-3 The Licensee may, as a condition of supply, require the Consumer to commit to a Contract Capacity for an initial period not exceeding 5 years. 4-4 The Licensee shall endeavour to make supply available upon 12 months of the Consumer accepting the commercial terms of supply. Public District Cooling Services Supply Code

The Arabic text is the legally binding version. The English translation is provided for guidance only.

Freshness not yet recorded

Related articles

Citing judgments

No judgments citing this article have been indexed yet.

Amendment timeline

No amendment history recorded.