Port Services Fees and Charges 3rd edition
Para. 3.3Status unknownSaudi ArabiaRegulation
Issued by Saudi Ports Authority — Mawani (mawani.gov.sa)
Storage Charges for Containers (exported loaded)
Item
No.
Description
Amount in
Rate
in
riyals
(Per
20ft
container)
Amount in
Rate
in
riyals
(Per
40ft
container)
Unit
The first 3 days following
the date of the container's
arrival at the port
Exempted
Exempted
per day or
part
thereof
From day 4 to day 10
per day or
part
thereof
From day 11 to day 15
per day or
part
thereof
From day 16 and beyond
per day or
part
thereof
Item
No.
Description
Amount in
Rate
in
riyals
per
20ft
container
Amount in
Rate
in
riyals
per
40ft
container
Unit
The first 10 days following
the date of the container's
arrival at the port
Exempted
Exempted
per day or
part
thereof
From day 11 to day 14
per day or
part
thereof
From day 15 to day 20
per day or
part
thereof
From day 21 and beyond
per day or
part
thereof
4. Additional Services:
Any additional service shall be charged (the actual cost +10%), and the person
requesting the service shall provide the necessary materials. The actual cost
shall be calculated as follows:
- The charges for used equipment shall be according to the annex of Table
(B).
- The wage of a worker is 10 Rate in riyals per hour or part thereof.
- The wage of a skilled worker or technician is 20 Rate in riyals per hour or
part thereof.
- The wage of an engineer or a supervisor is 30 Rate in riyals per hour or part
thereof.
*The exemption period for official holidays stipulated in this Item shall, pursuant
to the decision of the Minister of Transport, Chairman of the Board of Directors
of the Saudi Ports Authority, No. (1749.34) dated 15/05/1425H, be five days
only, two days before Eid and the three days of Eid.
Charges of Transit and Transshipment Services
Charges for Transit and Transshipment Services Collected from the
Ship owner or the Agent
Charges for handling transit and transshipped cargo
Item No.
Description
Rate
in
riyals
Unit
General cargo
per ton or cubic meter
or
part
thereof,
whichever is higher
Note:
- General cargo shall include all cargo, except vehicles, self-propelled
equipment, livestock, bulk cargo, or cargo loaded onto containers, flatbeds,
or trailers.
- General cargo the handling of which requires special equipment or treatment
shall be subject to the charges stipulated in (1.1) above as well as to charges
for any additional services rendered thereto according to (Four) of this table.
- General cargo handled using container cranes shall be charged three times
the charges stipulated in (1.1) above.
1.2 The charges of refrigeration services for chilled and frozen cargo. Such
charges shall be collected in addition to the storage charges stipulated in
(3) of this table:
Item No.
Description
Rate in riyals Unit
For
any
period
during the first three
days
per ton or part thereof
From the fourth day 10
per ton or part thereof/day
or part thereof
1.3 Self-propelled vehicles and equipment shall be charged according to their
weight as follows:
Item No.
Description
Rate
in
riyals
Unit
Less than 3 tons
per unit
From 3 to 10 tons
per unit
More than 10 and up to
40 tons
per unit
More than 40 tons
per unit
Note:
- Trailer heads shall be subject to (1.3) above, and the trailer attached to the
head shall be subject to (1.6).
- Automobiles and self-propelled vehicles which cannot be driven to or from
the ship for any reason, including lack of fuel therein or unsuitability of the
ship, shall be charged three times the charges stipulated in (1.3) above.
- Tracked vehicles must be mounted on trailers or flatbeds and shall be subject
to (1.6). If such vehicles are equipped in a manner that will not cause damage
to the port, they shall be subject to (1.3) above.
1.4 Livestock:
Item
No.
Description
Rate in riyals Unit
Sheep
per head
Other Livestock
per head
The Arabic text is the legally binding version. The English translation is provided for guidance only.