Saudi Arabian Grid Code May 2024
Para. 1.3.1Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
The Grid Code applies to the TSP and to all Users of the Grid, including all
persons/parties to whom any individual section of the Grid Code applies. In
specific the following:
(i)
The Transmission Service Provider (TSP);
(ii)
Generators;
(iii)
Distribution Entities; and
(iv)
Directly-connected Customers.
1.3.2 The provisions under this Code apply to Users seeking new Connection, or
modification of an existing Connection, to the Transmission System. Users
currently connected to the Transmission System may have been designed to
different standards and, therefore, may not be able to comply in whole or in
Chapter 1 - General Conditions
The Saudi Arabian Grid Code
Updated Version: May 2024
part with some or all of these conditions. Such Users should seek Derogation
by following the procedure set out in (1.11).
Grid Code Implementation and Enforcement
1.4.1 The TSP shall be responsible for the Grid Code implementation and
enforcement.
1.4.2 For the above purposes, the TSP may need access to the services and
facilities of Users or to issue instructions to Users in order to implement and
enforce the Grid Code (for example, to isolate or disconnect Plant or
Apparatus, etc.). All Users, therefore, are required not only to abide by the
letter and spirit of the Grid Code, but also to provide the TSP with such rights
of access, services and facilities and to comply with such instructions as the
TSP may reasonably require to implement and enforce the Grid Code.
1.4.3 Each party shall, at all times in its dealings with the other parties to the Grid
Code, act in good faith and in accordance with the established Good Industry
Practices.
Settlement of Disputes
In case of a dispute between the TSP and a User about any provision of the
Grid Code or any issue relating to that provision, the TSP and the User shall
first try to settle it bilaterally by making all reasonable endeavors for resolving
the dispute. If they cannot resolve the dispute bilaterally, the dispute parties
will proceed to deal with the dispute according to the procedure prescribed for
this purpose in the Electricity Law or guidelines issued by the Regulator.
Unforeseen Circumstances
If circumstances arise which the provisions of the Grid Code have not
foreseen, the TSP shall, to the extent practicable, consult all Affected Users in
an effort to muster consensus on the action required. If agreement between
the TSP and such Users cannot be reached in the time available, the TSP
shall determine the best course of action. Each User shall comply with all
instructions given to it by the TSP following such a determination provided
that the instructions are consistent with the then current technical parameters
of the relevant User’s System registered under the Grid Code. The TSP shall,
as soon as reasonably practicable following the occurrence of the unforeseen
Chapter 1 - General Conditions
The Saudi Arabian Grid Code
Updated Version: May 2024
circumstance(s), notify all relevant details thereof to the GCSC for
consideration as laid down in (1.10).
Suspension of Grid Code Provisions
The provisions (in part or in whole) of the Grid Code may be suspended
under abnormal conditions or pursuant to any directions given by the
Regulator or the Government.
Illegality and Partial Invalidity
If any provision of the Grid Code should become or be declared unlawful or
partially invalid for any reason, the validity of all remaining provisions of the
Grid Code shall not be affected.
Force Majeure
The Arabic text is the legally binding version. The English translation is provided for guidance only.
Freshness not yet recorded