Saudi Arabian Grid Code May 2024
Para. 1.9.1Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
A Participant shall not be considered to be in Default with respect to that
Participant’s obligation(s) under the Grid Code, other than the obligation to
pay money when due, if that Participant is prevented from fulfilling its
obligation(s) by Force Majeure. The defaulting Participant shall give notice
and the full particulars of such Force Majeure to the other concerned party (or
parties) in writing or by telephone as soon as reasonably possible after the
occurrence of the Force Majeure. Telephone notices given shall be confirmed
in writing as soon as reasonably possible and shall specifically state full
particulars of the Force Majeure, the time and date when the Force Majeure
occurred, and when the Force Majeure is reasonably expected to cease. The
Participant affected shall, however, exercise due diligence and all necessary
efforts to remove such disability and fulfill its obligations under the Grid Code.
1.9.2 Mere economic hardship shall not be considered Force Majeure. Acts of
negligence or wrongdoings shall also be excluded from Force Majeure.
The Grid Code Supervisory Committee (GCSC)
1.10.1 The TSP shall constitute and host the Grid Code Supervisory Committee
(GCSC) in accordance with the guidelines of the Regulator. The GCSC shall
be a standing body carrying out the functions referred to in (1.10.2) below.
1.10.2 The GCSC shall:
(i)
keep the Grid Code and its working under review;
Chapter 1 - General Conditions
The Saudi Arabian Grid Code
Updated Version: May 2024
(ii)
review all suggestions for amendments to the Grid Code which the
Regulator or any Participant may submit to the GCSC for
consideration from time to time or the GCSC initiates at its own;
(iii)
make recommendations to the Regulator for amendments to the Grid
Code which the GCSC feels are necessary or desirable and record
the reasons for the recommendations;
(iv)
issue guidance in relation to the Grid Code and its implementation,
performance, and interpretation upon the reasonable request of any
Participant;
(v)
consider what changes are necessary to the Grid Code arising out of
any unforeseen circumstances referred to it by the TSP under (1.6);
and
(vi)
review and make recommendation to the Regulator for final decision
on any request that a Grid Participant submits to the GCSC to seek
Derogation from any provision(s) of the Grid Code.
1.10.3 The GCSC shall be a stakeholder representative committee and shall consist
of the following members:
(i)
a Chairman and three (3) persons appointed by the TSP;
(ii)
a person appointed by the Regulator;
(iii)
two (2) persons representing Generators each having Generating
Station with a total Registered Capacity exceeding 500 MW;
(iv)
one person representing Generators each having Generating Station
with a total Registered Capacity 500 MW or less;
(v)
one person representing each Distribution Entity in the Kingdom of
Saudi Arabia, in total four (4);
(vi)
one person to represent Directly-connected Customers;
(vii)
one person to represent King Abdullah City for Atomic and Renewable
Energy (KACARE); and
(viii)
one person to represent Principal Buyer.
1.10.4 The GCSC shall establish and comply at all times with its own rules and
procedures relating to the conduct of its business, which shall be approved by
the Regulator and published by the GCSC within three (3) months of the
formation of the GCSC.
The Arabic text is the legally binding version. The English translation is provided for guidance only.
Freshness not yet recorded