Saudi Arabian Grid Code May 2024
Para. 2.3.1Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
General Provisions
2.3.1.1 A User seeking a new, or modification of an existing, Connection, to the Grid
shall secure a proper Connection Agreement with the TSP by following the
Chapter 2 - Connection Code
The Saudi Arabian Grid Code
Updated Version: May 2024
procedure specified in this section, prior to the actual Connection to the Grid.
This procedure is depicted in Figure 2.6, page 45.
2.3.1.2 The TSP shall establish the procedures for the processing of User
applications for new, or modification of an existing, Connection to the Grid.
The TSP will also set out the time for Connection after receiving all the
required information from the applicant.
2.3.1.3 The time periods for a User’s new, or modification of an existing, Connection
shall be negotiated and agreed upon upfront, between the TSP and the User,
in every case. Users will be connected to the Transmission System based on
Grid Impact Studies.
2.3.1.4 The conditions under this section apply to Users seeking new Connections to
the Transmission System. Users currently connected to the Transmission
System may have been designed to different standards and, therefore, may
not be able to comply in whole or in part with some or all of these conditions.
Such Users should seek Derogations in accordance with the provisions of
(1.11) of Chapter 1: General Conditions. However, these conditions shall be
applied to Users if new installations or modifications (e.g. in the Excitation
System, etc.) are introduced on the User Site.
2.3.1.5 All Plant and Apparatus at the Connection Point shall comply with the relevant
TSP standards, or in their absence, other IEC, ANSI, or IEEE standards,
unless modified by any provision in the applicable Connection Agreement.
2.3.1.6 The Transmission System voltage level at which a User will be connected and
the Busbar configuration which a User’s System uses will depend upon, but
not limited to, the following:
(i)
the size of the Generating Units and the number of Generating Units
comprised in the User System (for Generators);
(ii)
the size of the MW Demand at the Connection Point (for Distribution
Entities and Directly-connected Customers);
(iii)
consistency with future development of the Transmission System as
well as the coordinated planning of the Transmission System and of
the Distribution System/User System;
(iv)
proximity to the existing Transmission System; and
(v)
the cost of the proposed Connection.
2.3.1.7 The method of Connection used may exceed the relevant standards where
this is required by the User and is acceptable to the TSP.
Chapter 2 - Connection Code
The Saudi Arabian Grid Code
Updated Version: May 2024
2.3.1.8 The TSP shall deliver or take electric Energy at the Connection Point and
shall not be responsible in any manner whatsoever beyond that point.
2.3.1.9 In case of a dispute, the TSP shall try first to settle it bilaterally through
negotiation with the User. If cannot settle it, the TSP will deal with the dispute
according to the procedures and mechanisms prescribed by the Regulator for
this purpose.
The Arabic text is the legally binding version. The English translation is provided for guidance only.