Saudi Arabian Grid Code May 2024
Para. 2.3.5Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
Connection Agreement
The Connection Agreement between the User and the TSP shall meet the
following basic conditions:
(i)
The TSP and the User shall comply with the Grid Code in letter and
spirit.
(ii)
The User shall submit reports containing technical and financial
information as required in the various sections of the Grid Code.
(iii)
The TSP shall provide the User the relevant information in accordance
with its statutory and regulatory obligations.
(iv)
The User shall provide to the TSP estimated details on the types of its
loads and the estimated profile of each major load (e.g. air
conditioning, combined heat and Power, motors, and drives, etc.).
(v)
The User shall provide the TSP technical diagrams of the required
Connection as stated in this chapter or the application form.
(vi)
The User shall provide the TSP details of Safety and Protection
schemes at the User facilities and for the Connection Point.
(vii)
The Connection Agreement with the User shall also clearly specify the
operation and maintenance boundary between the User and the TSP.
(viii)
For NPP, the TSP and the Generators shall agree on a protocol to
exchange information in order to assess the operability of the Nuclear
Generating Stations off-site power supplies and to calculate the
operational availability of the same as required in the Nuclear Safety
Analysis.
(ix)
For Battery Energy Storage System (BESS), the Connection
Agreement shall specify if each part of the hybrid designs shall be
assessed as: (i) a separate Connection; or (ii) to be integrated as one
Connection. All parts of the hybrid design could be completely new or
some of them are existing. The existing Generation facility must
continue to comply with the technical requirements in force when said
production facility was originally connected, unless otherwise specified
in the Connection Agreement of new facilities.
Chapter 2 - Connection Code
The Saudi Arabian Grid Code
Updated Version: May 2024
2.3.6 Submittals Prior to the Commissioning Date
The following shall be submitted by the User prior to the Commissioning date,
pursuant to the terms and conditions and schedules specified in the relevant
Connection Agreement:
(i)
specifications of major Equipment not included in the Standard
Planning Data and Detailed Planning Data.
(ii)
details of the Protection arrangements and settings referred to in
(iii)
copies of all Safety Rules and instructions applicable to the User’s
Equipment and a list of Safety Representatives, pursuant to the
requirements of (4.10.8);
(iv)
Electrical Diagrams of the User’s Equipment at the Connection Point
as described in (2.7.4);
(v)
information that will enable the TSP to prepare the Connection Point
Drawings, referred to in (2.7.4);
(vi)
a list of the names and telephone numbers of authorized
representatives, including the confirmation that they are fully
authorized to make binding decisions on behalf of the User, for
Significant Incidents pursuant to the procedures specified in section
4.5: Operational Liaison in Chapter 4: Operating Code;
(vii)
proposed Maintenance Program;
(viii)
Commissioning Tests procedures for the Connection Point and the
User Development; and
(ix)
Site Test reports, clearance and readiness for Energization of the
proposed Connection Plant and Equipment.
The Arabic text is the legally binding version. The English translation is provided for guidance only.