Regulatory Framework for Renewable Energy Generation
Para. 5.3Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
REG Inspection & Meter Installation
When all civil and electrical works of the REG System have been completed and
the REG System is ready for energization:
a- The applicant shall submit a REG Inspection Application which informs the
Service Provider that the REG System is ready for inspection. The REG
Inspection Application shall indicate all preliminary information indicated in the
REG System Connection Process as well as the date from which the REG
System is available for the inspection.
b- On an agreed date, the Service Provider shall perform an on-site inspection
to check that the REG System is built and installed according to the provided
documentation and in compliance with the terms of the REG system
Connection Agreement and the applicable national electric codes and
standards.
c- If the REG System Inspection has a positive outcome, the Service Provider
shall install the metering system(s) according to the Metering Code and the
Service Provider’s Codes of practice for Metering for the Connection Point
and the Monitoring of Energy Production by the REG Systems.
d- Following successful completion of the REG System Inspection and the
installation of the meter(s), the Service Provider shall issue a Final
Operational Notification, which certifies that the REG System is compliant with
the Regulatory framework and that the electricity production can start.
Public
Regulatory Framework for Renewable Energy Generation for Self-Consumption
In case the full compliance of the REG System cannot be established from the
sole information and documents provided by the applicant:
a- The Service Provider may ask the Eligible Consumer to carry out specific tests
to demonstrate full compliance.
b- The Service Provider shall deliver a Limited Operational Notification which
allow the energization and use of the connection for the sole scope of
performing these compliance tests.
c- During the period of validity of the Limited Operational Notification, the Eligible
Consumer is allowed to use the connection and to exchange power with the
grid only for the purpose of the tests and according to a scheduling agreed
with the Service Provider.
d- At the positive completion of the tests, the Service Provider shall issue the
Final Operation Notification.