Saudi Arabian Grid Code May 2024
Para. 4.2.1Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
Introduction
4.2.1.1 This section deals with Demand forecasting for operational purposes, and
lays down the procedures to be followed and data to be supplied by Users to
the TSP to enable the TSP to forecast Demand on the Transmission System
for the period ranging from five (5) years ahead down to real time operation.
4.2.1.2 This section also deals with the provision of data on Demand Control in the
Operational Planning Phase, the Programming Phase, Control Phase, and
the Post Control Phase.
4.2.1.3 The TSP shall be responsible for developing Demand Forecasts for the
Operational Planning Phase after taking into account the Demand Forecasts
supplied by Distribution Entities and Directly-connected Customers.
Chapter 4 - Operating Code
The Saudi Arabian Grid Code
Updated Version: May 2024
4.2.1.4 In the Programming Phase and Control Phase, the TSP shall develop its own
Demand Forecasts after taking into account, information to be furnished by
Distribution Entities, Directly-connected Customers, and Generators.
4.2.2 Definitions
4.2.2.1 In this section, a reference to Year 0 shall mean the current calendar year,
Year 1 shall mean the next calendar year, Year 2 shall mean the calendar
year after Year 1, and so forth.
4.2.2.2 A reference to data being supplied on an hourly basis shall refer to it being
supplied for each period of 60 minutes ending on the hour.
4.2.2.3 Reactive Power Demand shall include the series reactive losses of the User
System bus but exclude any network susceptance and any reactive
compensation on that System. The TSP shall obtain the lumped network
susceptance and details of the reactive compensation from the data supplied
by the User as provided in Chapter 3: Planning Code.
4.2.3 Objectives
The objectives of this section are to specify:
(i)
the requirements for Grid Users to provide Demand and Generating
Plant output data to the TSP to enable it to plan and maintain
sufficient level of Generation Capacity and Operating Margin in the
System to meet Demand; and
(ii)
the factors which the TSP will consider when forecasting Demand
during the Operational Programming and Control Phases.
The Arabic text is the legally binding version. The English translation is provided for guidance only.