Saudi Arabian Grid Code May 2024
Para. 4.3.4Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
Planning of Generating Unit Outages
4.3.4.1 The Outage planning process in respect of a Generating Unit shall commence
not later than five (5) years prior to the scheduled Operational Date or from
the date of the relevant agreements, whichever is the later. The process shall
culminate in developing of the following three Programs scheduled over the
time scales indicated against each:
(i)
Committed Outage Program, covering real time up to end of Year 1;
(ii)
Provisional Outage Program, covering Year 2-3; and
(iii)
Indicative Outage Program, covering Year 4-5.
The time horizon for planning of Generation Outages is shown in Figure 4.2
below.
Chapter 4 - Operating Code
The Saudi Arabian Grid Code
Updated Version: May 2024
Figure 4.2. Program horizon for Generating Unit Outages
4.3.4.2 In rolling over the Generation Outage Program from one year to the next, for
every year (except, in any such case, to the extent that the Generator is
reasonably responding to changed circumstances), the procedure set out
below is to be followed:
(i)
submissions by the Generator for Year 2 should reflect the current
Provisional Outage Program for Year 3; and
(ii)
submissions by the Generator for Year 1 should reflect the current
Provisional Outage Program for Year 2.
4.3.4.3 The procedure set out below is to be followed in each calendar year.
4.3.4.4 By the end of March Year 0
(i)
Generators shall provide the TSP in writing, for each Generating Unit,
the following details of Planned Outages and estimates of probabilities
of Forced Outages for including in the Committed, Provisional, and
Indicative Outage Programs as defined in (4.3.4.1) above:
(a)
identity of the Generating Units concerned;
(b)
MW unavailable (and MW that will still be available, if any,
notwithstanding the Outage);
(c)
expected duration of the Outage;
Year 4 and Year 5
Indicative
Outage
Program
Year 2 and Year 3
Provisional
Outage
Program
March till end -Year 1
Committed
Outage
Program