Saudi Arabian Grid Code May 2024
Para. 4.2.5Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
Transmission System Forecasts
4.2.5.1 The following factors will be taken into account by the TSP when conducting
Demand Forecasts in the Programming Phase and Control Phase:
Chapter 4 - Operating Code
The Saudi Arabian Grid Code
Updated Version: May 2024
(i)
historic Demand data including Transmission System losses;
(ii)
socioeconomic growth projections of the country;
(iii)
weather forecasts and the current and historic weather conditions;
(iv)
the incidence of major Events or activities which are known to the TSP
in advance;
(v)
Embedded Generating Unit/Station Schedules;
(vi)
Demand Control of five (5) MW or more proposed to be exercised by
Distribution Entities and Directly-connected Customers and of which
the TSP has been informed; and
(vii)
other information supplied by the Users.
4.2.5.2 The TSP will prepare unbiased forecasts of the Transmission System
Demand using a sound forecast methodology which will take into account the
above factors to the maximum possible extent.
Outage Planning
4.3.1 Introduction
4.3.1.1 This section specifies conditions, requirements, and procedures that the TSP
and Users shall follow to match Generation Capacity with Forecast Demand
on the Transmission System over various operational planning horizons in
order to achieve, to the maximum possible degree, the Reliability and
Security standards expected of the TSP.
4.3.1.2 The section mainly concens with the following:
(i)
the planning, coordination, and approval of scheduled and un-
scheduled Outages of the Generating Unit and the Transmission
System; and
(ii)
the provision of planning parameters to the TSP by Generators for
operational planning purposes only.
4.3.1.3 The provisions of this section shall apply to all proposed Outages that may
affect the ability of a Generating Unit to achieve its full Registered Capacity
appropriate to each Registered Fuel in accordance with its Registered
Operating Characteristics.
4.3.1.4 This section also mandates the Generators to inform the TSP of any other
proposed maintenance of a Generating Unit or any associated Power Station
Plant or Apparatus, which can affect the availability of System Services from
that Generating Unit.
Chapter 4 - Operating Code
The Saudi Arabian Grid Code
Updated Version: May 2024
4.3.1.5 In complying with the various provisions of this section, each Grid Participant
shall act reasonably, in good faith, and in accordance with Good Industry
Practices when planning Outages for its own system and also when
coordinating the scheduling of these Outages with those of the others. This
will be imperative to avoid a situation arising in which a Participant is obliged
to request an Outage during the Outage Planning process as a consequence
of that Participant’s not having planned its Outages in accordance with Good
Industry Practice.
4.3.2 Definitions
In this section, a reference to Year 0 shall mean the current calendar year,
Year 1 shall mean the next calendar year, Year 2 shall mean the calendar
year after Year 1, and so forth.
4.3.3 Objective
The key objective of Outage Planning is to promote the developing and
implementing of an orderly Generation and Transmission Outage Program
that is consistent with reliable and secure operation of the Transmission
System, and also addresses the needs of the Generators for Plant
maintenance and resource limitations. In specific, to define the following:
(i)
the procedure for formal notification of Outages by Generators to the
TSP; and
(ii)
the procedures that the TSP will use to prepare, review, and notify the
Indicative, Provisional, and Committed Outage Programs for the Grid.
The Arabic text is the legally binding version. The English translation is provided for guidance only.