Saudi Arabian Grid Code May 2024
Para. 4.2.4Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
Data Required by the TSP for Operational Demand Forecasting
4.2.4.1 Each User shall supply data to the TSP in relation to that User’s Demand and
Active Energy relating to various operational phases as stated in the relevant
parts of this section. Figure 4.1 highlights timescales involved with each
Phase.
Chapter 4 - Operating Code
The Saudi Arabian Grid Code
Updated Version: May 2024
Figure 4.1. Description and time flow of various operational planning phases
Operational Planning Phase
(i) Distribution Entities and Directly-connected
Customers provide forecast of Active Demand and
Energy for the next 5 years to the TSP.
(ii) The TSP develops 5-year Demand Forecast
Programming Phase
(i) Each first day of business week, Distribution Entities
and Directly-connected Customers provide to the TSP,
MW profile, on hourly and Connection Point basis, of
Demand Control for the next 8 weeks
(ii) The TSP develops 8-weeks Demand Forecast
Control Phase
(i) Distribution Entities and Directly-connected
Customers provide to the TSP Demand changes, on
hourly and Connection Point basis.
(ii) The TSP develops day-ahead Demand Forecast
Post-Control Phase
Distribution Entities and Directly-connected Customers
provide to TSP, on hourly and Connection Point basis,
the actual Demand Control carried out.
End
Year 0
Start of
Year1
By End
March
8 weeks
ahead of
Schedule
Day
Day
ahead of
Schedule
Day
Subsequent
Day
Schedule
Day
Chapter 4 - Operating Code
The Saudi Arabian Grid Code
Updated Version: May 2024
4.2.4.2 Operational Planning Phase (Year 1 to Year 5)
(i)
No later than 31 January each year, the TSP shall notify each User in
writing of the following (for the current year and for each of the
succeeding five (5) calendar years:
(a)
the date and time of its expected annual peak Demand at
Annual Maximum Demand Conditions; and
(b)
the date and time of its expected annual minimum Demand at
Average Conditions.
(ii)
By end of March each year, every User, as further elaborated below,
shall provide to the TSP in writing, the forecast information listed
below for the current year and each of the succeeding five (5)
calendar years:
(a)
for each Distribution Entity (summed over all Connection
Points) and for each Directly-connected Customers (at the
Connection Point), the hourly forecast profile of Active Power
Demand for the day of that User’s Maximum Demand and for
the specified day of the annual peak Demand of the TSP, both
at their respective Annual Maximum Demand Conditions;
(b)
for each Distribution Entity (summed over all Connection
Points) and for each Directly-connected Customer (at the
Connection Point) the annual Active Energy requirements for
Average Conditions segregated into different usage categories
such as, residential, commercial, Government, industrial,
agriculture, street lighting, hospitals, etc., wherever practicable;
(c)
for each Distribution Entity (summed over all Connection
Points) and Directly-connected Customer (at the Connection
Point) the hourly forecast profile of Active Demand for the
specified day of the minimum Demand of the TSP at Average
Conditions;
(d)
individual Connection Point Demand (Active Power) and
Power Factor at Annual Maximum Demand Conditions for the
annual peak hour at the Connection Point and at the specified
hour of the annual peak of the TSP Demand; and
Chapter 4 - Operating Code
The Saudi Arabian Grid Code
Updated Version: May 2024
(e)
individual Connection Point Demand (Active Power ) and
Power Factor at Average Conditions at the specified hour of
the annual minimum Demand of the TSP.
(iii)
If the Busbar at a Connection Point is expected to be operated in
separate sections, separate sets of Forecast Data for each section
shall be provided to the TSP.
(iv)
The TSP will use the information supplied to it in preparing Forecast
Demand information for the next five years and for use in its
operational planning.
4.2.4.3 Programming Phase (1 to 8 weeks ahead of the Schedule Day)
For 1 to 8 weeks ahead of the Schedule Day, each Distribution Entity and
Directly-connected Customer shall supply to the TSP, in writing, by 10:00
hours each first day of business week, hourly MW profiles of the amount and
duration of their proposed use of Demand Control which may result in a
Demand change of five (5) MW or more on an hourly and Connection Point
basis.
4.2.4.4 Control Phase
Each Distribution Entity and Directly-connected Customer shall inform the
TSP of any Demand Control which may result in a Demand change of five (5)
MW or more averaged over any hour on any Connection Point which is
planned after 10:00 hours, and of any changes to the planned Demand
Control notified to the TSP prior to 10:00 hours as soon as possible after the
formulation of the new plans.
4.2.4.5 Post-Control Phase
Each Distribution Entity and Directly-connected Customer shall supply to the
TSP in writing by 10:00 hours each day Active and Reactive Power data in
terms of MW profiles for the previous calendar day of the amount and
duration of actual Demand reduction achieved from the use of Demand
Control of five (5) MW or more (averaged over any hour on any Connection
Point), on an hourly and Connection Point basis.
The Arabic text is the legally binding version. The English translation is provided for guidance only.