Planning of Transmission System Outages
4.3.5.1 The procedure set out in this subsection shall be followed in each calendar
year for planning of Transmission System Outages (see Figure 4.3 below).
Figure 4.3. Program Horizon for Transmission System Outages
4.3.5.2 The TSP shall plan Transmission System Outages required in Years 2 and 3
as a result of construction or refurbishment works taking due account of the
known requirements. The planning of Transmission System Outages required
Year 2 and Year 3
Indicative
Outage
Program
For Year 1
Provisional
Outage
Program
March till end -Year 0
Committed
Outage
Program
Chapter 4 - Operating Code
The Saudi Arabian Grid Code
Updated Version: May 2024
in Years 0 and 1 ahead will, in addition, take into account Transmission
System Outages required as a result of maintenance.
4.3.5.3 Transmission System Outages and Generating Unit Outages shall, during
Years 2 and 3 but not in Year 1 or before, be coordinated so that, in general,
the Generating Unit Outages shall take precedence over Transmission
System Outages but subject always, in any particular case, to the TSP
discretion to determine otherwise on the basis of reasons relating to the
proper operation of the Transmission System.
4.3.5.4 Indicative Outage Planning – Planning for Year 2 and 3
By the end of September Year 0, the TSP will draw up a draft Transmission
System Outage Program covering the period Years 2 and 3 for TSP’s internal
use and will notify each User in writing of those aspects of the draft plan
which may operationally affect such User including, in particular, proposed
start dates and end dates of relevant Transmission System Outages. The
TSP will indicate to a Generator where a need may exist to use inter-tripping
or other measures including restrictions on the Scheduling and Dispatch of
Generating Units to allow the Security of the Transmission System to be
maintained within the statutory or regulatory requirements.
4.3.5.5 Provisional Operational Planning - Planning for Year 1
The plan produced pursuant to (4.3.5.4) will become the draft Transmission
System Outage Program for Year 1 when, by the passage of time, Year 2
becomes Year 1. Each calendar year, the TSP shall update the draft
Transmission System Outage plan and shall, in addition, take into account
Outages required as a result of maintenance work.
(i)
By the end of June Year 0, the TSP will draw up a draft Provisional
Transmission Outage Program and will inform each User of any
potential restrictions which may affect it and generally the impact on
the Transmission System in Year 1. The draft Provisional
Transmission Outage Program shall take into account the conditions
of the Connection Agreement of each NPP which are related to
Nuclear Safety Analysis.
Chapter 4 - Operating Code
The Saudi Arabian Grid Code
Updated Version: May 2024
(ii)
Where a User objects to the proposed restrictions or impact notified to
it in (i) above, equivalent provisions to those set out in (4.3.4.5[ii]) will
apply.
(iii)
Between the end of June and the end of September Year 0, the
TSP will draw up a final Transmission System Outage Plan covering
Year 1.
(iv)
By the end of September Year 0, the TSP will issue the final
Transmission System Outage Plan for Year 1. The TSP will notify
each User in writing of those aspects of the plan which may
operationally affect that User including, in particular, proposed start
dates and end dates of relevant Transmission System Outages. The
TSP will also indicate where a need exists to use inter-tripping,
emergency switching, emergency load management, or other
measures including restrictions on the Scheduling and Dispatch of
Generating Units to allow the Security of the Transmission System to
be maintained within allowable limits.
4.3.5.6 Committed Outage Planning - Year 0 down to the Programming Phase
The Transmission System Outage plan for Year 1 issued under section
(4.3.5.5) will become the Committed Outage Program for Year 0 when by the
passage of time Year 1 becomes Year 0.
4.3.5.7 Nuclear Safety shall be the first concern of the Programming Phase.
4.3.5.8 Programming Phase
(i)
By 14:00 hours each last day of business week, the TSP shall
update the Transmission System Outage plan for the following one (1)
week period beginning on the first day of business week.
(ii)
The TSP will notify each User in writing of those aspects of the plan
which may operationally affect such User including in particular
proposed start dates and end dates of relevant Transmission System
Outage. The TSP will also indicate where a need exists to use inter-
tripping, emergency switching, emergency load management, or other
measures including, restrictions on the Dispatch of Generating Units
to allow the Security of the Transmission System to be maintained
within allowable limits.
Chapter 4 - Operating Code
The Saudi Arabian Grid Code
Updated Version: May 2024
(iii)
During the Programming Phase, the User and the TSP will inform
each other immediately if there is any unavoidable requirement to
depart from the Outage Plan and actions determined and notified
under this subsection.