Saudi Arabian Grid Code May 2024
Para. 4.9.6Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
Commissioning Tests
4.9.6.1 Commissioning Tests is one of the final activities under project
implementation which is carried out to test all Equipment, Protection Schemes
and other systems to verify the correct functioning of the User Development.
The TSP will witness the Commissioning Tests. After the Commissioning
Tests and their acceptance by the TSP, the User facility is considered ready
for Energization.
4.9.6.2 The following Commissioning Test procedure shall be followed:
(i)
All the tests specified in the Connection Agreement shall be carried
out in the presence of designated personnel of the TSP or its
authorized representative(s). All test results must be signed by such
personnel or representative(s). All tests shall be performed in
accordance with the Commissioning Test schedules pre-approved by
the TSP.
(ii)
The User shall prepare and submit a Commissioning Test
schedule/plan, specifying the acceptance criteria, for review and
approval of the TSP, at least six (6) months before the schedule date
for these tests.
(iii)
The User shall provide test Equipment that has sufficient capacity and
accuracy to properly perform the tests.
(iv)
The User shall submit to the TSP the particulars of personnel
assigned for the Commissioning Tests and valid calibration certificates
of all the test Equipment for TSP’s review and approval.
(v)
The User shall fill-in any form required by the TSP and submit the
same to the TSP for review and acceptance.
(vi)
The TSP shall witness the Commissioning Tests, and verify all test
results recorded in the Site test reports.
(vii)
The TSP shall request the User to rectify deficiencies, if any, observed
during the Commissioning Tests.
(viii)
The User shall mark-up all the “issued for construction” drawings
indicating the modifications done to wiring etc., during the
Commissioning Tests.
Chapter 4 - Operating Code
The Saudi Arabian Grid Code
Updated Version: May 2024
(ix)
One set of marked-up drawings shall be kept at the facility or in the
control room for any trouble shooting until the "as-built" drawings are
prepared and turned over by the User to the TSP.
(x)
The TSP shall proceed with the routing of Energization certificate on
completion of the Commissioning Tests. The facility will be ready for
Energization once the Energization certificate is duly signed and
issued by the TSP, subject to the User's completing of any remaining
formalities.
The Arabic text is the legally binding version. The English translation is provided for guidance only.