Saudi Arabian Grid Code May 2024
Para. 4.8.5Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
Operational Test Program
4.8.5.1 Within two (2) months after the first meeting and at least one (1) month prior
to the date of the proposed Operational Test, the Test Group shall submit to
the TSP, the Test Proponent, and the Affected Users a proposed Test
Program which shall contain the following:
(i)
a plan for carrying out the test;
(ii)
the procedure to be followed for the test, including the manner in
which the test is to be monitored;
(iii)
list of responsible persons, including those responsible for
coordinating on Safety, when necessary, and who will be involved in
carrying out the test;
(iv)
allocation of all testing costs among the Affected Users; and
(v)
such other matters as the Test Group may deem appropriate and
necessary and are approved by the management of the Affected
Users.
4.8.5.2 If the proposed Test Program is acceptable to the TSP and the Affected
Users, the final Test Program shall be prepared and the test shall proceed
accordingly. Otherwise, the Test Group shall revise the Test Program to make
it acceptable.
4.8.5.3 If the Test Group is unable to develop a Test Program or reach a consensus
in implementing the Test Program, the TSP shall determine whether it is
necessary to proceed with the test to ensure the Security of the Transmission
System.
4.8.5.4 The Test Coordinator shall be notified in writing, as soon as possible, of any
proposed revision or amendment to the Test Program prior to the day of the
proposed test. If the Test Coordinator decides that the proposed revision or
amendment is meritorious, he shall notify the TSP, the Test Proponent, and
the Affected Users to act accordingly for the inclusion thereof. The Test
Program shall then be carried out with the revisions or amendments if the
Test Coordinator receives no objections.
4.8.5.5 If conditions are abnormal on the scheduled day for the test, the Test
Coordinator may recommend a postponement or rescheduling of the test.
Chapter 4 - Operating Code
The Saudi Arabian Grid Code
Updated Version: May 2024
4.8.6 Operational Test Report
4.8.6.1 Within one (1) month or a shorter period as the Test Group may agree after
the conclusion of the test, the Test Proponent shall prepare and submit a Test
Report to the TSP, the Affected Users, and the members of the Test Group.
4.8.6.2 After the submission of the Test Report, the Test Group shall stand dissolved.
Testing to Monitor, Investigate, and Verify Performance
4.9.1 Introduction
4.9.1.1 In order to discharge its responsibilities for safe, secure, and economic
operation of the Transmission System, the TSP will need to carry out certain
testing to monitor, investigate, and verify the performance of Users’ Plant.
4.9.1.2 The TSP shall treat all information and data collected from User pursuant to
the provisions of this section as confidential.
4.9.2 Objective
The primary objective is to establish a procedure for verifying that the Users
are operating within their design, operating and other contractual
requirements, as specified in the relevant Connection Agreement between the
User and the TSP.