Saudi Arabian Grid Code May 2024
Para. 4.8.4Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
Establishing of the Test Group
4.8.4.1 Within one (1) month after the acceptance of a Test Request, the TSP shall
notify the Test Proponent, and the Affected Users of the proposed test. The
notice shall contain the following:
(i)
the purpose and nature of the proposed test, the extent and condition
of the Equipment involved, the identity of the Test Proponent, and the
Affected Users;
(ii)
an invitation to nominate representative(s) for the Test Group to be
established to coordinate the proposed test; and
Chapter 4 - Operating Code
The Saudi Arabian Grid Code
Updated Version: May 2024
(iii)
if the test involves work or testing on (E)HV Equipment, the
responsible person(s) for Safety Assurance shall be informed and the
Safety procedures specified in section 4.10: Cross-boundary Safety
Assurance shall be followed.
4.8.4.2 The Test Proponent and the Affected Users shall nominate their
representative(s) to the Test Group within one (1) month after receiving the
notice from the TSP.
4.8.4.3 If an Affected User fails to nominate its representative within the period
stipulated in (4.8.4.2), the TSP will issue a reminder to that User asking the
User to nominate his representative to the Test Group within one (1) week’s
time. If the User still does not nominate its representative, The TSP may
decide to proceed with the proposed test and may appoint another TSP
person to the Test Group to represent the interests of that User.
4.8.4.4 The TSP shall establish a Test Group and appoint a Test Coordinator, who
shall act as chairman of the Test Group. The Test Coordinator may come
from the TSP or the Test Proponent.
4.8.4.5 The members of the Test Group shall meet within one (1) month after the
Test Group is established. The Test Coordinator shall convene the Test
Group as often as necessary.
4.8.4.6 The agenda for the meeting of the Test Group shall include the following:
(i)
the details of the purpose and nature of the proposed Test and other
matters included in the Test Request;
(ii)
evaluation of the Test Procedure as submitted by the Test Proponent
and making necessary modifications to come up with the final Test
Procedure;
(iii)
the possibility of scheduling the proposed test simultaneously with any
other test(s) and with Equipment maintenance which may arise
pursuant to the Maintenance Program requirements of the TSP or the
Users; and
(iv)
the economic, operational, and risk implications of the proposed test
on the Transmission System, and the Scheduling and Dispatch of the
Generating Unit/Station.
4.8.4.7 The Test Proponent and the Affected Users (including those which are not
represented in the Test Group) shall provide the Test Group, upon request,
Chapter 4 - Operating Code
The Saudi Arabian Grid Code
Updated Version: May 2024
with such details as the Test Group reasonably requires for carrying out the
proposed Operational Test.