Saudi Arabian Grid Code May 2024
Para. 4.9.7Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
Generating Unit Capability Tests
Test Requirements
4.9.7.1 Tests shall be conducted, in accordance with the agreed procedure and
standards, to confirm the compliance of Generating Units for the following:
(i)
capability of Generating Units to operate within their Registered
Generation Planning Parameters;
(ii)
capability of the Generating Units to meet the applicable requirements
of the Grid Code;
(iii)
capability to deliver the System Service(s) that the Generator has
agreed to provide; and
(iv)
Availability of Generating Units in accordance with their capability
Declaration.
4.9.7.2 All tests shall be recorded and witnessed by the authorized representatives of
the TSP, Generator, and/or User.
4.9.7.3 The Generator shall demonstrate to the TSP the reliability and accuracy of
the test instruments and Equipment to be used in the test.
4.9.7.4 The TSP may at any time issue instructions requiring tests to be carried out
on any Generating Unit. All tests shall be of sufficient duration and shall be
conducted no more than twice a year except when there are reasonable
grounds to justify the necessity for further tests.
4.9.7.5 If a Generating Unit fails the test, the Generator shall correct the deficiency
within an agreed period to attain the relevant registered parameters for that
Generating Unit.
4.9.7.6 Once the Generator achieves the registered parameters of its Generating Unit
that previously had failed the test, it shall immediately notify the TSP. The
Chapter 4 - Operating Code
The Saudi Arabian Grid Code
Updated Version: May 2024
TSP shall then require the Generator to conduct a new test in order to verify
that the appropriate parameter has been restored to its Registered value.
4.9.7.7 If a dispute arises relating to the failure of a Generating Unit to pass a given
test, the TSP, the Generator, and/or User shall seek to resolve the dispute
among themselves. Failing to agree, the dispute shall be resolved in
accordance with the Regulatory Guidelines for this purpose.
Tests to be Performed
4.9.7.8 Reactive Power Test shall demonstrate that the Generating Unit meets the
registered Reactive Power capability requirements as specified in Chapter
2: Connection Code. The Generating Unit shall pass the test if the
measured values are within ± five (5) percent of the Capability as
registered with the TSP.
4.9.7.9 Primary Response Test shall demonstrate that the Generating Unit has the
capability to provide Primary Response. The Generating Unit shall pass the
test if the measured response in MW/Hz is within ± five (5) percent of the
required level of response within five (5) seconds.
Fast Start Capability Test shall demonstrate that the Generating Unit has
the capability to Start-up, Synchronize with the Grid within ten (10) minutes,
and be loaded up to its offered capability. The Generating Unit shall pass
the test if it meets the Fast Start capability requirements.
Black Start Test shall demonstrate that the Generating Plant with Black
Start capability can implement a Black Start procedure. To pass the test,
the Generating Unit shall start on its own, Synchronize with the Grid, and
carry load without the need for external Power supply.
Declared Data Capability Tests shall demonstrate that the non-Renewable
Resource Generation can be Scheduled and Dispatched in accordance
with the Declared Data. To pass the test, the Unit shall satisfy the ability to
achieve the Declared Data.
In case of RRG, Declared Data Capability Tests may be undertaken by
continuous monitoring of the environmental conditions, Output parameters
and Grid parameters or maybe Tests called at discrete points in time.
Dispatch Accuracy Test shall demonstrate that the Generating Unit meets
the relevant Generation Scheduling and Dispatch Parameters as per new
clause 2.5.5.16. The non-Renewable Resource Generation shall pass the
test if:
Chapter 4 - Operating Code
The Saudi Arabian Grid Code
Updated Version: May 2024
(i)
in the case of Synchronization, the process is achieved within ± five
(5) minutes of the registered Synchronization time;
(ii) in the case of Synchronizing Generation (if registered as a Generation
Scheduling and Dispatch Parameters), the Synchronizing Generation
achieved is within an error level equivalent to ±2.5% of Net Declared
Capability;
(iii) in the case of meeting Ramp Rates, the actual Ramp Rate is within ±
ten (10)% of the registered Ramp Rate;
(iv) in the case of meeting Load Reduction rates, the actual Load
Reduction rate is within ± ten (10)% of the registered Load Reduction
rate;
(v) in the case of minimum base load Generating Units, variation of + ten
(10)% will be acceptable; and
(vi) in the case of all other Generation Scheduling and Dispatch
Parameters, values are within ± 1.5% of the declared values.
The Renewable Resource Generation shall pass the test if they comply with
the test foreseen under (iv).
The TSP may advise the Generators one or more of the following tests
also, if considered necessary by the TSP:
(i)
deep voltage transient by short-circuit;
(ii) Generating Unit’s changeover to House Load Operation;
(iii) Generating Unit House Load Operation for one hour;
(iv) step response of Generating Unit voltage;
(v) Power System Stabilizer (PSS); and
(vi) overload Capacity.
System Service Acceptability Test shall determine the committed services
in terms of parameter quantity or volume, timeliness, and other
operational requirements. Generators providing System Services shall
conduct the test or define the committed service. However, monitoring by
the TSP of System Service performance in response to System-derived
inputs shall also be carried out.