Saudi Arabian Grid Code May 2024
Para. 5.1.1Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
This chapter specifies the responsibilities and obligations of the TSP and
Users with respect to Scheduling and Dispatch of Generating Units and other
Demand resources. It sets out the procedure for supplying of timely and
accurate information by the Users to the TSP, the TSP’s preparing and
issuing of Generation Schedules, and issuing of Dispatch Instructions.
5.1.2 This chapter is divided into two sections: Generation Scheduling and
Generation Dispatch. Section 5.3, Generation Scheduling, deals with
submitting of Availability Notices and relevant information by Generators and
any modification to them subsequently, if required. The section also describes
the procedure to be followed by the TSP for preparing and issuing of
Generation Schedule to specify which Generating Units may be required for
Dispatch. This section also details the Special Actions that the TSP may
require from users to match supply with Demand and ensure the requisite
Stability and Reliability on the Grid. Section 5.4, Generation Dispatch, deals
with Dispatch of Generating Units and executing of other Special Actions to
minimize cost of Supply procurement while ensuring the availability of
adequate level of Operating Margin and other System Services.
Objective
The objective of this chapter is to enable the TSP to Schedule and Dispatch
adequate Generation resources to meet electricity Demand at all times at
minimum cost while ensuring the integrity of the System, as well as the
requisite levels of supply Quality and Reliability.
Generation Scheduling
5.3.1 Scheduling Process
5.3.1.1 The TSP will carry out Scheduling daily to develop a Generation Schedule for
the next following Schedule Day. This process will be phased and iterative to
allow appropriate interactions of the TSP with Generators and other Users to
match Demand with supply on an instant-by-instant basis with the requisite
Chapter 5 - Scheduling and Dispatch Code
The Saudi Arabian Grid Code
Updated Version: May 2024
levels of supply Quality and Reliability. The process of Generation Scheduling
is shown in Figure 5.1 on page 140.
5.3.1.2 The Schedule Day will begin at 00:00 hours on the Schedule Day, and will
last for 24 hours until 00:00 hours on the next day.
5.3.1.3 Grid Users must submit sufficient data as detailed in this chapter to allow the
TSP to prepare a Generation Schedule. Since the TSP is required to match
Generation, transfers, and Demand on an instant-by-instant basis, some
additional information may be required by the TSP to accomplish this
objective. Details of any reasonable additional information requirements will
be notified by the TSP to the relevant Users, as the need arises.
5.3.1.4 Data submissions to the TSP shall normally be made electronically in
accordance with the provisions of Chapter 6: Data and Information Exchange
Code as well as of any agreement between the TSP and the User. In the
event of failure of the electronic systems for submitting of data to the TSP,
data submissions may be made by fax.
5.3.1.5 If, any changes occur after a User has supplied information to the TSP
pursuant to (5.3.2, 5.3.3, and 5.3.4) below, then the User shall inform the
TSP, without delay, of such changes.
5.3.1.6 Based on the Declarations and information supplied (and revised afterwards
as the case may be) by the Users, the TSP will develop a Generation
Schedule for the next following Schedule Day and inform the relevant Users
accordingly.