Saudi Arabian Grid Code May 2024
Para. 5.3.6Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
The Generation Schedule
5.3.6.1 Each day by 15:00 hours, the TSP shall develop, by means of an appropriate
Scheduling program or process, a Generation Schedule for the next following
Schedule Day that will utilize the last valid set of Scheduling and Dispatch
Parameters for the Generating Unit as applicable.
5.3.6.2 The Generation Schedule shall be prepared by the TSP to Schedule such
Generating Units for which the TSP had received Availability Notice to
achieve the following:
(i)
minimize the cost of procuring the required Electricity in accordance
with the relevant Power Purchase Agreements to match the Forecast
Demand;
(ii)
match at all times (to the extent possible) the Forecast Demand with
an appropriate Operating Margin;
(iii)
match minimum electricity Demand levels together with a sufficient
Minimum Demand Regulation; and
(iv)
maintain Frequency Control.
5.3.6.3 The TSP will give priority in dispatch for cogeneration and Sustainable
Resource Generation plants taking into consideration the conditions under
clause 5.3.6.2.
5.3.6.4 Factors to be taken into account
In preparing the Generation Schedule, the TSP will consider the following
factors:
(i)
Forecast Demand and its geographical distribution;
(ii)
Declared MW capabilities of Generators;
(iii)
System Services capabilities of Generators;
(iv)
Operating Characteristics of Generators;
(v)
System Constraints;
(vi)
Generation costs of each Generating Unit;
(vii)
Generating Unit Outages;
(viii)
Voltage Control requirements;
(ix)
System Stability factors;
(x)
Operating Margin requirements;
(xi)
System losses;
Chapter 5 - Scheduling and Dispatch Code
The Saudi Arabian Grid Code
Updated Version: May 2024
(xii)
System Frequency Control requirements;
(xiii)
any testing to be carried out;
(xiv)
operation of Generating Unit to provide a sufficient Minimum Demand
Regulation; and
(xv)
any other factors as may be reasonably considered by the TSP to be
of relevance to the Generation Schedule.
5.3.6.5 The Generation Schedule issued to each Generator by the TSP shall contain
the information relating to the Generating Units of that Generator only.
5.3.6.6 The Generation Schedule will be only indicative, and will be intended to
provide a guide to the expected output requirements from Generators and will
not be construed as Dispatch Instructions or orders by itself.
5.3.6.7 The information contained in the Generation Schedule will indicate on an
individual Generating Unit basis the period for which it is Scheduled during
the following Schedule Day.
5.3.6.8 Revision to Scheduling and Dispatch Data
At any time between 10:00 hours each day and the expiry of the next
following Schedule Day, a Generator may submit to the TSP any revisions to
the submitted data:
(i)
If the revised Generation Data is received by the TSP before 15:00
hours on the day prior to the relevant Schedule Day, the TSP shall, if
possible, take into account the revised Availability Notice in preparing
the Generation Schedule.
(ii)
If the revised Generation Data is received by the TSP at or after 15:00
hours but before the end of the next following Schedule Day, the TSP
shall, if it re-Schedules the Generating Units, take into account the
revised Availability Notice in that re-Scheduling.
(iii)
Between 15:00 hours on the day before the Schedule Day and 1 hour
before real time, the Saudi Sustainable Energy Control Center may
send updated Declarations on behalf of Renewable Resource
Generation based on updated renewable infeed forecasts. The TSP
shall update the Generation Schedule to take into account these
updated Declarations.
The Arabic text is the legally binding version. The English translation is provided for guidance only.