Saudi Arabian Grid Code May 2024
Para. 7.9.11Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
The Metering Equipment shall be restored to service and proved to be
operating within the prescribed limits of accuracy as soon as is reasonably
practicable.
Main and Check Metering
7.10.1 For each Connection, Main and Check Metering shall be provided. Main and
Check Meters shall be from different manufacturers and shall operate from
separate CT and VT windings.
7.10.2 The provisions of this chapter shall apply equally to Main and Check Meters.
7.10.3 CT and VT windings and cables connecting such windings to Main Meters
shall be dedicated for such purposes and such cables and connections shall
be securely sealed.
7.10.4 The Main Meter, Check Meter and additional burdens shall have separately
fused VT supplies.
7.10.5 The loss of voltage to the Meters should give an alarm.
Timekeeping
7.11.1 All Metering Installation shall record time, based on Saudi Arabian Standard
Time.
7.11.2 The commencement of each Demand Period shall be within ±10 seconds of
the true time.
7.11.3 The duration of each Demand Period shall be accurate to within ± 0.1%
except where time synchronization has occurred in that period.
Chapter 7 - Metering Code
The Saudi Arabian Grid Code
Updated Version: May 2024
Metering Access and Sealing
7.12.1 Metering Equipment and associated communications Equipment shall be
located in a dedicated and secure cabinet located in an area readily
accessible, free from obstructions, and well-lit by artificial light(s).
7.12.2 The cabinet shall conform to service conditions as specified in TSP’s
Standard 01-TMSS-01. These design measures shall at least include
protection from moisture and dust and from physical damage including
vibration and provide appropriate temperature control.
7.12.3 The cabinet shall be equipped with a lock and shall be clear-fronted and
sealed by the TSP. The control of this sealing shall conform to procedures as
laid down by the TSP from time to time. This seal can only be broken by or
with the consent of the TSP.
7.12.4 Internal access to Metering Equipment, enclosures, and the associated
communications equipment shall be in accordance with procedures specified
by the TSP.
7.12.5 The Users shall permit the TSP or its representatives, the rights to enter
upon, pass through, and remain upon any part of such User property to the
extent necessary for the purposes of performance under this Code. Users
shall make all reasonable arrangements and provisions to facilitate the TSP
or its representatives in exercising such rights.
7.12.6 The right of access provided pursuant to (7.12.5) above shall also include the
right to bring any vehicles, Plants, machinery and maintenance or other
materials as may be reasonably required by the TSP for the performance of
obligations under the Metering Code.
7.12.7 The seals that the TSP shall use on Metering installations must be strong and
durable, not prone to easy or accidental damage or early deterioration owing
to weather or operating environment.
7.12.8 Seals shall be capable of being fixed easily and shall be designed and
constructed to prevent undetectable tampering under normal usage and must
not permit their removal or undoing without breaking.
7.12.9 Seals shall be identifiable by unique numbers and TSP logos that are legible
and traceable to those affixing these.
Chapter 7 - Metering Code
The Saudi Arabian Grid Code
Updated Version: May 2024
Damage, Tampering, or Unauthorized Interference with Metering
Equipment
7.13.1 The TSP shall examine Metering installations periodically to ensure that all
security seals are intact and that the Metering Equipment is functioning
properly and without any signs of damage, tampering, or unauthorized
interference.