Saudi Arabian Grid Code May 2024
Para. 7.8.7Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
Meters
(i)
Meters shall be of the three-element type independent for each phase,
rated for the required Site, comply with IEC Standard 62052-11:
Electricity Metering Equipment (AC) — General requirements, tests,
and testing conditions or IEC Standard 62053-21: Electricity Metering
Equipment (AC) — Particular requirements (or their equivalent
ANSI/IEEE/Saudi national/TSP standards), for static watt-hour meter
and other types of Meters, and shall be of the accuracy class of 0.2 or
equivalent. The Meters shall measure and locally display at least the
kW, kWh, kvar, kvarh, and cumulative Demand, with additional
features such as time-of-use, maintenance records, Power Quality
monitoring, and pulse output. The pulse output for remote metering
must be for all the major measurement features.
(ii)
The Meters may be digital or analogue as per the agreement between
the TSP and the User.
Chapter 7 - Metering Code
The Saudi Arabian Grid Code
Updated Version: May 2024
(iii)
A cumulative record of the parameters measured shall be available on
the Meter. Bi-directional Meters shall have two such records available.
If combined Active Energy and Reactive Energy Meters are provided,
then a separate record shall be provided for each measured quantity
and direction. The loss of auxiliary supply to the Meter shall not erase
these records.
(iv)
Data storage shall be provided internally or externally to the Meter by
way of a data logger which shall provide an output per measured
quantity.
Testing and Inspection of Metering Installations
7.9.1 All Meters, CTs and VTs, shall be tested for accuracy at initial
Commissioning. Tests shall also be carried out thereafter at intervals not less
frequently than every twelve (12) months for Main Meters and not less than
six (6) years for CTs and VTs, or as specified in the relevant Connection
Agreement to verify that their operation is within the prescribed limits of error.
7.9.2 Test terminals shall be provided for Main and Check Meters to facilitate on
site tests.
7.9.3 Meters shall be tested in service and should be tested out of service only if
the accuracy is suspected to be not within the limits.
7.9.4 A User may request a test and shall bear the full cost of such testing if the
Meter is found to be not operating within the prescribed limits. Tests will be
organized such that all relevant parties are notified of the tests, and are
invited to witness them, if required. Test results will be made available to the
User involved.
7.9.5 Meters may also be tested by the TSP whenever the TSP notices or suspects
an error in metering.
7.9.6 In carrying out of tests on Main Meters, any interruption to measurement will
be taken account of and appropriately compensated. The testing
measurement will be taken by another Meter and will be appropriately
compensated.
7.9.7 Care shall be taken in carrying out tests to ensure that any Interruption to
measurement is avoided or minimized.
7.9.8 Certified test Equipment and reference standards (traceable to a recognized
national or international standard) shall be used in such tests and if, by
Chapter 7 - Metering Code
The Saudi Arabian Grid Code
Updated Version: May 2024
agreement, it is deemed necessary, an approved independent laboratory may
be employed.
7.9.9 Where a test indicates that an error exceeds the limits of error prescribed in
the applicable standards, then these errors shall be recorded before promptly
adjusting, repairing or renewing the Metering Equipment (or part thereof) or
replacing any defective components.
7.9.10 Pursuant to (7.9.9) above, the reading taken previously, and all charges
based therein, shall be corrected on the basis of this test for a period as set in
the applicable Connection Agreement.