Saudi Arabian Grid Code May 2024
Para. 2.7.3Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
Site and Equipment Identification and Labeling
2.7.3.1 The TSP shall provide to each User details of TSP’s current numbering and
nomenclature system to enable the User to plan the numbering and
nomenclature of its own (E)HV Plant and Apparatus on the Connection Site.
2.7.3.2 The party installing Plant and/or Apparatus shall be responsible for providing
and installing of clear and unambiguous labels showing the Site and
Equipment identification at its respective System.
2.7.3.3 The numbering and nomenclature of each item of Plant and/or Apparatus
shall be included in the Operation Diagram prepared for each Site.
2.7.3.4 For TSP Plant and/or Apparatus on a User Site
(i)
If the TSP intends to install its E(HV) Plant and/or Apparatus on a
User Site, it shall notify the relevant User of its intent in writing by
showing the proposed Plant and/or Apparatus, with clear numbers and
nomenclature, on an Operation Diagram and by giving date of the
proposed installation, at least six (6) months ahead of the proposed
installation.
(ii)
the relevant User will confirm to the TSP in writing within one (1)
month of the receipt of such notification, either its acceptance of the
TSP proposal or objection(s), if any, by stating the reasons for the
objection(s).
(iii)
the relevant User will not install, or permit the installation of, any
(E)HV Plant and/or Apparatus on such User Site which has numbering
and/or nomenclature which could be confused with that of (E)HV Plant
and/or Apparatus of the TSP already on that User Site or about which
the TSP has notified to that User that it intends to install on that Site.
2.7.3.5 For User Plant and/or Apparatus on the TSP Sites
(i)
If a User intends to install its (E)HV Plant and/or Apparatus on a TSP
Site, it shall notify the TSP of its intent in writing by showing the
proposed Plant and/or Apparatus, with clear numbers and
nomenclature, on the Operation Diagram and by giving date of the
proposed installation, at least six (6) months ahead of the proposed
installation.
(ii)
the TSP will respond in writing to the User within one (1) month of the
receipt of the notification either confirming its acceptance of the User
Chapter 2 - Connection Code
The Saudi Arabian Grid Code
Updated Version: May 2024
proposed numbering and nomenclature or, if they are not acceptable,
by giving details of the numbering and nomenclature which the User
shall adopt for that (E)HV Apparatus.
2.7.3.6 Changes
If the TSP intends to change the existing numbering or nomenclature of either
its own (E)HV Plant and/or Apparatus on a User Site or of the User (E)HV
Plant and/or Apparatus on a TSP Site:
(i)
the provisions of paragraph (2.7.3.4) shall apply to such change of
numbering or nomenclature of the (E)HV Plant and/or Apparatus of
the TSP with any necessary amendments to those provisions to reflect
that only a change is being made; and
(ii)
in the case of a change in the numbering or nomenclature of (E)HV
Plant and/or Apparatus of the User on a TSP Site, the TSP shall notify
the User of the numbering and/or nomenclature that the User shall
adopt for that (E)HV Plant and/or Apparatus at least six (6) months
prior to the change being needed and the User will respond in writing
to the TSP within one (1) month of the receipt of the notification,
confirming receipt.
In either case, the notification shall indicate the reason for the proposed
change.