4.7.3.1 Emergency Plans shall allow for quick and orderly recovery from a Partial or
Total Shutdown, with minimum impacts on the Users.
Chapter 4 - Operating Code
The Saudi Arabian Grid Code
Updated Version: May 2024
4.7.3.2 All Contingency and/or Emergency Plans shall be periodically verified by
actual tests to the greatest practical extent. When such tests can cause
undue risk or undue cost to a User, the TSP shall take such risks or costs into
consideration when deciding whether to conduct the tests or not. Tests shall
be carried out at a time that is least disruptive to the Participants. The costs of
these tests shall be borne by the respective asset owner(s). The TSP shall
ensure the coordination of the tests in consultation with all Affected Users.
4.7.3.3 Users shall comply with the TSP’s requirements for Contingency and
Emergency Plans.
4.7.3.4 The TSP shall set the requirements for Automatic and Manual Load Dropping
after consulting and agreeing on the schedules with the Users. The Users
shall make available options and schemes to comply with these requirements.
4.7.3.5 The TSP shall be responsible for determining all operational limits on the
Transmission System, updating these periodically, and making these
available to the User.
4.7.3.6 The TSP shall conduct necessary system studies regularly to determine the
effect that various component failures would have on the Reliability of the
Transmission System. At the request of the TSP, Distribution Entities shall
also perform requisite system studies on their part(s) of the network and
make the results available to the TSP.
4.7.3.7 Following Emergency operations as may be necessary to protect the integrity
of the Transmission System or the Safety of Equipment and human life, the
Participants shall work diligently towards removing the cause of the
Emergency and the supply shall be restored immediately after the Emergency
Conditions have passed.
4.7.3.8 Emergency drills shall be conducted at least once a year to familiarize all staff
responsible for Emergency and System Restoration activities with the
Emergency and System Restoration procedures. The drills shall simulate
realistic emergency situations. A drill evaluation shall be performed and
deficiencies in procedures and responses shall be identified and corrected.
4.7.3.9 The TSP shall develop and maintain Contingency Plans to manage system
contingencies and emergencies that are relevant to the performance of the
Transmission System. Such Contingency Plans shall be developed in
consultation with all Users involved in the Transmission System, shall be
Chapter 4 - Operating Code
The Saudi Arabian Grid Code
Updated Version: May 2024
consistent with internationally accepted practices, and shall include but shall
not be limited to the following:
(i)
under frequency load shedding;
(ii)
under voltage load shedding;
(iii)
disasters management (natural disasters, or other unexpected
events), including the necessary minimum load requirements;
(iv)
Forced Outages at all Connection Points, and
(v)
supply restoration.
The Arabic text is the legally binding version. The English translation is provided for guidance only.
Freshness not yet recorded