Saudi Arabian Grid Code May 2024
Para. 2.0Status unknownSaudi ArabiaRegulation
Issued by Saudi Electricity Regulatory Authority (sera.gov.sa)
Hz).
2.5.5.21 On-load tap changing facilities shall be required on Generator step-up
transformers for Dispatch of Reactive Power. The transformer voltage ratio,
tapping range, and step sizes must be such that the Reactive Power
requirements specified in (2.5.5.9) are fully complied with.
2.5.5.22 The TSP shall be entitled to acquire such operational metering, control
parameters, and Plant data as it may reasonably require for the purposes of
discharging its statutory and regulatory obligations.
2.5.5.23 A Generating Unit shall be capable of:
a) Under Steady State Conditions: continuous uninterrupted operation for
the voltage variation specified in (2.4.3).
b) Under Transient Conditions:
i.
For Synchronous Generating Units withstanding Faults on the
Transmission System which may cause the voltage at the Connection
Point to drop to between 0% and 80% of the nominal voltage for a
period of up to 300 millisecond in any one phase or combination of
phases, followed by a period of one (1) second where voltage may
vary in the range 80-110% of the nominal voltage, and followed by a
30-minute period where voltage may vary in the range specified in
ii. For Power Park Modules: withstanding Faults on the Transmission
System which may cause the voltage at the Connection Point to drop
to 0% for a period of up to 300 millisecond in any one phase or
combination of phases, followed by a period where voltage may vary
in a range specified by:
at the lower side, a linear restoration of the voltage towards 80% of
the nominal voltage within 1.3 second after initial voltage drop.
and at the upper side, not exceed 120% of nominal voltage for
more than 1s in any one phase, and followed by a 30-minute
period where voltage may vary in the range specified in (2.4.3).
These requirements are applicable to BESS in both charging and
discharging modes. Above 0.9 p.u., the BESS must be capable to
maintain normal operation. Within the PPM Fault withstand capability
Chapter 2 - Connection Code
The Saudi Arabian Grid Code
Updated Version: May 2024
area, the BESS facility must provide maximum voltage support by
delivering a controlled amount of additional reactive current to ensure
that the BESS contributes to the voltage stabilisation within the design
capabilities of the BESS.
Figure
The Arabic text is the legally binding version. The English translation is provided for guidance only.